Annual report 2014
Since 1886
Total transformer capacity of power sources, MVA | Length of overhead transmission lines (on circuits), km | Length of cable lines, km | Number of employees, people | ||
---|---|---|---|---|---|
1 | Vyborg Electric Networks | 1 688 | 8 219 | 360 | 573 |
2 | Gatchina Electric Networks | 1 891 | 7 498 | 227 | 536 |
3 | Kingisepp Electric Networks | 1 176 | 7 508 | 49 | 486 |
4 | St. Petersburg High-Voltage Electric Networks | 23 951 | 41 832 | 21 567 | 906 |
5 | New Ladoga Electric Networks | 644 | 4 487 | 1 328 | 546 |
6 | Suburban Electric Networks | 10 052 | 2 221 | 547 | 452 |
7 | Tikhvin Electric Networks | 619 | 4 959 | 40 | 337 |
8 | Cable Network | 6 900 | 73 | 18 895 | 1485 |
9 | Directorate of Objects under Construction | — | — | — | 118 |
10 | The name of the branch was changed to Energouchet by the decision of the Board of Directors of 13 March 2015 Location: St. PetersburgLuga Electric Networks |