The Program of innovative development

Lenenergo pays considerable attention to initiatives in the field of innovative development and implementation of R&D programs necessary for achievement of strategic objectives of the electric grid complex. The Company has adopted the Program of innovative development of Lenenergo for 2011-2016 approved by the Board of Directors (Minutes #2 of 29.07.2011, as amended by Minutes #8 of 27.08.2012).

In 2014, the Company approved the Policy of innovative development, energy saving and increase of power efficiency of Rosseti as the Company’s internal document (Order #338 of 29.07.2014). At present, Lenenergo conducts work on formation of the innovative development Program for 2015-2019 with reference to the investment program of the Company for 2015-2019.

The goal of the innovative development Program — development and implementation of new technologies, innovative products and services that meet global standards, to enhance the economic and energy efficiency of power supply.


Tasks of the innovative development Program

Formation of the system of corporate governance, focused on the development and implementation of new technologies, innovative products and services


Creation of the system of search and selection of fundamental innovative ideas, development and implementation of the mechanism for selection of priority topics for R&D activities


Creation of the mechanism for implementation of pilot projects for innovative technologies and launch of trial production of experimental high-tech electrical equipment


Ensuring the necessary conditions for replication of innovations on the scale of Lenenergo and Rosseti


Development of the mechanism for financing innovation at the expense of own funds and attracting of investors


Ensuring integration of the Program with core business processes of Lenenergo


Providing the necessary level of personnel potential of Lenenergo


Ensuring protection of the intellectual property of Lenenergo


Providing the system of information support of innovative processes management and monitoring of advancement of innovations in Lenenergo


Promotion of innovative projects in the fields of energy conservation, energy efficiency, economic efficiency and reliability of electricity supply in the distribution grid complex


Optimization of operating costs and reducing Company costs


Dynamics of expenses for implementation of the innovative development Program in key directions, RUB mln

Dynamics of expenses for implementation of the innovative development Program in key directions
3,724 RUB mln
Expenses for implementation of the innovative development Program in 2014

Trial operation of innovative equipment

In 2014, Lenenergo went on with trial operation of innovative equipment, including:
Equipment Expected result of implementation
Gas insulated switchgear 110 kV PASS MOH produced by ABB. Place of installation — substation 110 kV #80 Ust-Slavyanka of the Lenenergo branch St. Petersburg High-Voltage Electric Networks. Reduction of the area of placement of the equipment 110kV, reliability augmentation of power supply of consumers and reduction in engineering and construction works on installation of equipment at the substation 110 kV.
The system for determining fault location on transmission lines by wave method TWS FL produced by QUALITROL company (USA). Place of installation — OTL 110 kV Garbolovskaya-1, 2 of the Lenenergo branch St. Petersburg High-Voltage Electric Networks. Reduction of time for elimination of failures at electric power lines and reliability augmentation of power supply of consumers.
Signal transfer device of relay protective automatic equipment for power lines 6-110 kV— the result of development executed by JSC Avangard. Place of installation — substation 35 kV #13 Volkhov-Vasileostrovskaya, substation 110 kV #14 Baltiyskaya, substation 110 kV #104 Vasileostrovskaya of the Lenenergo branch St. Petersburg High-Voltage Electric Networks. Will allow retaining the existing devices of relay protection of OTL 6-110 kV with replacement of worn-out cord-insulated copper communication cables for fiber-optic communication lines.
Wire with protective insulation of series PZVG (produced by LLC Sevkabel-Engineering) and composite poles of series PK-110 with isolating traverses (produced by CJSC FENIKS-88). Place of installation — OTL 35 kV Shusharskaya-1 of the Lenenergo branch St. Petersburg High-Voltage Electric Networks. Compact OTL. Reliability augmentation of power supply of consumers.
Analyzer of dissolved gases in transformer oil Smart 9 (produced by Lumasense, USA). Place of installation — substation 110 kV #165 Petrogradskaya of the Lenenergo branch St. Petersburg High-Voltage Electric Networks. Fast fault detection for power transformers and increase their useful life, reliability augmentation of power supply of consumers.
Device for continuous monitoring of gas content in transformer oil SEVERON TM8 (produced by Qualitrol, USA). Place of installation — substation 110 kV #370 PGV-2 Svetlana of the Lenenergo branch St. Petersburg High-Voltage Electric Networks. Early detection of faults in power transformers and increase their useful life, reliability augmentation of power supply of consumers.
Automatic monitoring system of the insulation pollution of overhead lines MetrySense-4000 (produced by Metricom, Israel). Place of installation — OTL 110 kV Obukhovskaya-3/4 and OTL 110 kV Kudrovskaya-5/Oktyabrskaya-11 of the Lenenergo branch St. Petersburg High-Voltage Electric Networks. Will allow supervising distantly the level of pollution of overhead lines insulation and in a timely manner to clean it up in the areas of aggressive environment.

In 2014, the programs were implemented together with such higher education institutions as St. Petersburg State Polytechnic University, National Mineral and Raw University “Gorny”, St. Petersburg State Agrarian University, Ivanovo State Power University and National Research University “MEI”.

A total of 561 employees were trained on the professional development programs, which funding totaled RUB 4.3 mln, 25 employees were re-trained in higher education institutions for which RUB 9.1 mln was allocated.

R&D

Lenenergo has been implementing the program of research and development aimed at improving technologies and developing breakthrough solutions.

The main objective of the R&D Program is to create and develop a smart energy system with active-adaptive networks.


Tasks of the R&D Program:

Introduction of new technologies, innovative products and services


Decrease in wear of networks to the level of developed countries


Energy saving and power efficiency increase


Increase of economic efficiency and reliability of power supply in distribution networks


Optimization of operational expenses and decrease in Company costs


The list of facilities on which R&D results were introduced
Equipment, technology, material, system Details of the contract for development Nature of use (introduction, pilot operation application in activity) Object of introduction, pilot operation, division using in its activity Results of introduction, pilot operation, application in activity Effect
Signal transfer device of relay protective automatic equipment for power lines 6-110 kV Contract #11-12863 of 15.11.2011 with LLC Avangard Pilot operation (2014-2015)

Substation 35 kV #13 Volkhov-Vasileostrovskaya,

Substation 110 kV #14 Baltiyskaya,

Substation 110 kV #104 Vasileostrovskaya (branch of Lenenergo St. Petersburg High-Voltage Electric Networks)

By results of pilot operation By results of pilot operation
Transfer of distribution networks 10 kV on resistance neutral grounding Contract #12-1947 of 09.02.2012 with JSC STC UES Introduction (2013-2014) Substation 110 kV #75 Lakhta, #155 Piskarevka, #24 Rzhevka and #96 Ozero Dolgoye (branches of Lenenergo St. Petersburg High-Voltage Electric Networks, Cable Network and Suburban Electric Networks) Reduced damage of electric grid equipment. Increased reliability of cables and other elements of the grid. The effect was not determined due to insufficiently long period of operation
The list of exclusive rights (patents, registration certificates) on R&D results received in the reporting period
R&D protected by exclusive rights Details of exclusive right Details of the contract under which the R&D program was developed The status of receipt of exclusive rights documents (protected/ applied)
Database “Data on the technical condition of overhead lines 35-110 kV by results of instrumental ground surveys and laser aero scanning” State registration certificate of the database #2014620617 of 25.04.2014 Contract #11-14150 of 12.10.2011with CJSC OPTEN Limited Protected
Signal transfer device of relay protective automatic equipment for power lines 6-110 kV Application # 2014115494/20 (024303) of 17.04.2014 Contract # 11-12863 of 15.11.2011 with JSC Avangard Applied